South Pars Phases 20 and 21 project

South Pars Phases 20 and 21 project

South Pars Phases 20 and 21 project

Installation and pre-commissioning of all refinery facilities and Main Pipe rack including:

Earthworks: 244,000 cubic meters

Concreting: 47,000 cubic meters

Installation of steel structure: 11,000 tons

Installation of equipment: 3772 tons

Piping and insulation: 702,000 inches in diameter

Electricity and instrumentation: 2000 tons + 1000 km of cabling

Painting: 169,000 square meters